Building our Naples with Ryan Homes in Liberty Township Ohio
Sunday, October 25, 2015
Foundation and Plumbing
It has been a busy two weeks as the lot has gone from staked, to a hole with footers, and not the foundation is in. Our PM told us that the lumber will be dropped off on Tuesday and that the slabs should be poured on Monday. It's coming together quickly!
The house is wrapped in water proofing. This is from the back of the foundation.
Some of the plumbing from the rear.
We added the Egress window in the rear of the finished basement.
Straight ahead are the rough ins for the basement bath. It is a 3 piece rough in.
No comments:
Post a Comment